Crossrail: New Timelapse Footage Highlights Current Progress

With over half the escalators now installed in the new Elizabeth line stations, new timelapse footage and photos released by Crossrail highlights current progress.

17 escalators have been fully commissioned at Canary Wharf station and the framework for 37 more have been completed at Paddington, Bond Street, Tottenham Court Road, Farringdon and Liverpool Street. Together these combine to a length of 1,603 metres, the equivalent of one mile of escalators.

New Elizabeth Line Stations

In total, 81 escalators will be installed and commissioned at nine new Elizabeth line stations between Paddington and Woolwich, with a total length of 2.8 kilometres (2,802 metres). In addition, 54 lifts are being installed at these nine stations and all 40 stations on the Elizabeth line will have step-free access.

Related Post:  Mechan Sets Fundraising Goal to Mark Half Century

The longest escalator on the Elizabeth line will be at Bond Street – the 60 metre long escalator will carry passengers from Hanover Square near Oxford Street to platform level 25.7 metres below. The shortest escalator, at 18.5 metres, will be at Liverpool Street and take passengers from street level down into the Broadgate ticket hall. The 81 escalators have been installed at a 30 degree incline.

Station Escalators

Escalators in the new Elizabeth line stations will travel at a speed of 0.5 metres per second, with the exception of Canary Wharf’s escalators which travel at 0.75 metres per second as they have one less flat step at the top.

Related Post:  British Steel Wins Major Network Rail Contract Extension

Vanessa Hope-Lewis, Crossrail Lift and Escalator Field Engineer, said:

“Over 200 million passengers a year will use these escalators to access the newest addition to London’s transport network. As the Crossrail project passes 85% complete, the installation of these escalators is another step forward in the completion of the Elizabeth line ahead of its opening on time in December 2018.”

Original article © Crossrail.

FOR ALL THE LATEST INFORMATION, NEWS, IMAGES, VIDEOS AND ARTICLES ON ALL ASPECTS OF INFRASTRUCTURE, PLEASE CLICK HERE

News categories

17 Oct 2018
UK: Priti Patel MP Joins Rail Fellowship Programme
26 Sep 2018
CrossRail RORUNNER Systems Officially Handed Over to Transport for London
05 Sep 2018
Mechan Jacks Lift Expectations for Crossrail Trains
03 Sep 2018
Elizabeth Line: Opening of Central Section Delayed Until 2019
29 Aug 2018
Depot Safety Specialist Zonegreen Wins Bombardier Contract
02 Jul 2018
UK: New Maintenance Trains for London’s Elizabeth Line
29 Jun 2018
UK: Railway Industry Association Announces 2018 Conference
28 Mar 2018
TfL Orders Additional Trains for London’s Elizabeth Line
Subscribe to Railway-News
Get the latest contract alerts and Railway News emailed directly to your inbox.

We respect your privacy and take protecting it seriously.

Please tick to confirm you would like to receive emails we think may be of interest to you. We sometimes tailor the content you see to what we think you'll find interesting, and so monitor your interaction with our website and email content (find out more).