Network Rail Apologises as Waterloo Station Upgrade Works Overrun

Network Rail has now fully reopened Waterloo station after completing one of the largest and most complex upgrades in the station’s history.

However, due to safety critical work taking slightly longer than planned, Network Rail apologises to passengers for any delays to their journey and asks them to continue to check before they travel.

London Waterloo Upgrade
London Waterloo – Day 1 v Day 23 © Network Rail

Waterloo Station Upgrade

A 1,000-strong team of engineers and trackside staff have been working 24 hours a day for the last three and half weeks to complete the work this morning (Tuesday, 29 August).

During the three week project, platforms 1-4 were extended to accommodate longer, 10-car trains, creating more space for passengers.

The work was an essential part of the £800 million Waterloo and South West Upgrade which will boost capacity at the station by 30% by December 2018, providing space for another 45,000 passengers at morning and evening peaks.

Network Rail thanks passengers for their patience over August.

Becky Lumlock, route managing director at Network Rail, said:

“The work we have completed in three and a half weeks this August will benefit passengers for decades to come. The longer platforms will create space for longer trains, making journeys more comfortable for passengers, particularly at the busiest times of day.

“Over the next 16 months we’ll turn our attention to the final stages of the redevelopment of the former International Terminal. We’ll be working behind the scenes so that we can, by the end of next year, permanently bring the five extra platforms back into use for what will become a modern, high frequency commuter terminal fit for the 21st century.

“I’d like to personally thank passengers for their patience over the last few weeks, and apologise to disruption to their journeys this morning.  I’d also like to pay tribute to our 1,000 strong army of engineers and track workers who have delivered such an enormous project.”

Increased Capacity for the Future

Over the three and a half weeks there have been:

  • 180,000 hours worked
  • 1,270 metres of track laid
  • 230 metres of pre-cast concrete installed
  • 160 meters of new platform built
  • 7 miles of cable laid

Andy Mellors, managing director for South Western Railway, said:

“I’d like to thank our passengers for their patience over the past few weeks. It’s clearly been a challenging time but these improvement works will help us deliver the increased capacity needed for the future.

Rail passengers travelling from some stations in Kent are asked to check before travel today (Tuesday 29 August) as trains which had been scheduled to run into Waterloo while major improvement work is carried out in and around London Bridge will run to and from London Blackfriars instead. Passengers can check before they travel at www.nationalrail.co.uk.

Original article © Network Rail.

FOR ALL THE LATEST INFORMATION, NEWS, IMAGES, VIDEOS AND ARTICLES ON ALL ASPECTS OF INFRASTRUCTURE, PLEASE CLICK HERE.

Get your news featured on Railway-News

Please fill in the contact form opposite. A member of the team will be in touch shortly.







    We'd love to send you the latest news and information from the world of Railway-News. Please tick the box if you agree to receive them.

    For your peace of mind here is a link to our Privacy Policy.

    By submitting this form, you consent to allow Railway-News to store and process this information.

    Subscribe
    Follow Railway-News on LinkedIn
    Follow Railway-News on Twitter