Brides Glen – Overhead Line Bracket Arm Replacement
Mosdorfer Rails supplied the overhead line equipment for the replacement of six GRP bracket arms at Brides Glen on the Luas network. Working with Pod-Trak, the project involved the installation of galvanised steel bracket arms incorporating foot insulators, providing a solution consistent with arrangements already in use across sections of the existing system.


As part of the upgrade, the existing composite tie ropes were replaced with stainless-steel tie ropes and discreet insulators, reflecting the system’s current preferred arrangement. Connection components were carefully selected to ensure compatibility with the existing stitches and registration arms, allowing existing equipment to be retained wherever possible.



Cooper Crossing – Overhead Line System Modification
At Cooper Crossing, Mosdorfer Rails supplied the overhead line equipment for a project undertaken by Pod-Trak to modify the existing supporting arrangement following a developer’s request to remove the pole on the north side of the track.

The removal of the existing pole, which supported a traction feeder, required the opposite pole to be converted to a feeder pole. This involved replacing the existing pole with a feeder variant incorporating a street lighting adapter, alongside a change from the existing cross-span arrangement to a twin-track bracket arm system.
The works also required modifications to ducting, traction feeder cables and bonding, with the overall project designed to minimise disruption to the operation of the Luas network.
All overhead line equipment for the project was supplied by Mosdorfer Rails. The equipment was selected to provide compatibility and effective integration with the existing infrastructure, supporting the successful modification of the overhead line arrangement while maintaining continuity with the established system.
It has been great to work along side Pod-Trak, in these projects and we look forward to future collaboration with them.