Crossrail Europe’s Largest Infrastructure Project is Now Halfway Through its Construction Programme

Less than five years after works began on Crossrail, Europe’s largest infrastructure project today reached the halfway point of its construction. Atkins is involved in seven of the ten new major stations, and the western twin bored tunnels in a joint venture with Arup.

Prime Minister David Cameron, Mayor of London Boris Johnson and Crossrail Minister Stephen Hammond marked the occasion by visiting the £14.8 billion project, going 25 metres below ground to view progress at Crossrail’s Tottenham Court Road site. The station will be a key interchange with London Underground when trains run through central London from 2018.
Prime Minister David Cameron said: “Big infrastructure projects like Crossrail are vital for the economy of London and the rest of Britain. They are the foundation-stone on which business can grow, compete and support jobs – a massive 55,000 jobs in the construction phase of this project alone.”

London’s population is set to grow from 8.4 million today to around 10 million by 2030. Government, the Mayor of London and Transport for London are investing in Crossrail and other transport infrastructure to support access to jobs, education, housing and to boost economic growth.

Rob McCrae, framework director on Crossrail for Atkins said “As part of the Crossrail project team, Atkins is immensely proud of the significant progress made to date. Reaching this milestone is testament to all the hard work above and beneath the ground, as we deliver Europe’s largest infrastructure project.”

During 2014, Crossrail’s major civil engineering and tunnelling works will conclude and the focus will shift towards station construction, fit-out and implementing railway systems within the tunnels and stations. The train operator will then test and refine the systems before trains run from 2018.

View supplier

All the Latest News

Caltrain Completes Integrated Testing between San Francisco and San Jose

Caltrain Completes Integrated Testing between San Francisco and S...

Caltrain's electric trains have completed integrated testing between San Francisco and San Jose in California.

Siemens and Škoda Group to Deliver First ComfortJet Trains to Czech Railways

Siemens and Škoda Group to Deliver First ComfortJet Trains to Cze...

Siemens Mobility and Škoda Group are transferring the first new ComfortJet trains to Czech Railways ahead of passenger service this summer. 

East Midlands Railway to Refurbish Luton Airport Express Trains

East Midlands Railway to Refurbish Luton Airport Express Trains

East Midlands Railway (EMR) is investing 27.6 million GBP in a train refurbishment programme for the Luton Airport Express.

Scotland: Network Rail Invests £3.4 Million in Glenfinnan Viaduct

Scotland: Network Rail Invests £3.4 Million in Glenfinnan Viaduct

Network Rail is commencing a 3.4 million GBP investment project to repair the 123-year-old Glenfinnan Viaduct. 

Alstom to Supply Metropolis Trains for Santo Domingo Metro Extension

Alstom to Supply Metropolis Trains for Santo Domingo Metro Extens...

OPRET has contracted Alstom to supply new trains for the extension of Line 2 on the Santo Domingo Metro in the Dominican Republic. 

FCH2Rail Bi-Mode Hydrogen Train Completes Tests in Portugal

FCH2Rail Bi-Mode Hydrogen Train Completes Tests in Portugal

CAF has announced that the FCH2Rail project has completed testing of its bimodal hydrogen train on the rail network in Portugal. 

California High-Speed Rail Releases RFP for Electric Train Contract

California High-Speed Rail Releases RFP for Electric Train Contra...

The California High-Speed Rail Authority has approved the release of a Request for Proposals (RFP) to procure its electric high-speed trains.

Amtrak Issues RFI for Zero-Emission Rail Technologies

Amtrak Issues RFI for Zero-Emission Rail Technologies

Amtrak has issued a Request for Information (RFI) for solutions that could help transform its rail fleet with zero-emission technologies. 

Canada: Team Selected to Build Surrey Langley SkyTrain Stations

Canada: Team Selected to Build Surrey Langley SkyTrain Stations

British Columbia has selected South Fraser Station Partners to design and build eight new stations for the Surrey Langley SkyTrain project.

Chicago Metra Launches $332 Million Construction Plan for 2024

Chicago Metra Launches $332 Million Construction Plan for 2024

Chicago's commuter rail system, Metra, has announced a comprehensive list of construction projects planned for 2024.

California High-Speed Rail Releases Train Interior Design Renderings

California High-Speed Rail Releases Train Interior Design Renderi...

The California High-Speed Rail Authority has released new preliminary interior design renderings for its future train amenities. 

Spain: Talgo Delivers First Avril Trains to Renfe

Spain: Talgo Delivers First Avril Trains to Renfe

In Spain, Talgo has delivered its first Avril trains to Renfe following the completion of on-track testing. 

Caltrain Celebrates Electrification of 51-Mile Corridor

Caltrain Celebrates Electrification of 51-Mile Corridor

Caltrain, Balfour Beatty and PG&E have celebrated the start of testing across the fully electrified 51-mile Caltrain corridor. 

HS2 Launches Final Northolt Tunnel Boring Machine

HS2 Launches Final Northolt Tunnel Boring Machine

The fourth and final tunnel boring machine (TBM) being used to build the Northolt Tunnel has been launched under London.

PATH Forward to Enhance Rail Network in New Jersey

PATH Forward to Enhance Rail Network in New Jersey

PANYNJ has launched PATH Forward: a two-year programme to provide enhanced services and infrastructure on New Jersey's PATH rail network. 

Alstom Electric C-Series Train Starts Passenger Service in Perth

Alstom Electric C-Series Train Starts Passenger Service in Perth

The first of Alstom's electric C-series trains has entered passenger service in Perth for the Western Australia Railcar Program.

CN to Test EMD Mainline Hybrid Locomotive from Progress Rail

CN to Test EMD Mainline Hybrid Locomotive from Progress Rail

Canadian National (CN) has purchased a hybrid diesel-battery electric mainline locomotive from Progress Rail to reduce transport emissions.

Alstom to Deliver 35 Additional RER NG Trains to  Île-de-France Mobilités

Alstom to Deliver 35 Additional RER NG Trains to Île-de-France M...

Île-de-France Mobilités has contracted Alstom to supply an additional 35 RER NG trains for Line E in Paris.

UK: Siemens Mobility to Deliver Signalling and Control Systems for Network Rail

UK: Siemens Mobility to Deliver Signalling and Control Systems fo...

Siemens Mobility has secured first place on Network Rail’s Train Control Systems Framework, which will upgrade Britain's rail network.

Switzerland: LEB Orders 4 Multiple-Unit Trains from Stadler

Switzerland: LEB Orders 4 Multiple-Unit Trains from Stadler

Swiss rail operator, Lausanne-Echallens-Bercher (LEB) has ordered four additional Be 4/8 multiple-unit trains from Stadler. 

Belgium: De Lijn, CAF and OTIV Test AI to Enhance Tram Safety

Belgium: De Lijn, CAF and OTIV Test AI to Enhance Tram Safety

Flemish transport operator, De Lijn is collaborating with CAF and OTIV to deploy AI technology to enhance the safety of trams in Belgium. 

Siemens Mobility’s Mireo Plus B Battery Hybrid Trains Start Service in Germany

Siemens Mobility’s Mireo Plus B Battery Hybrid Trains Start...

Siemens Mobility's Mireo Plus B battery hybrid trains have begun regular service for SWEG in the Ortenau region of Germany. 

Île-de-France Mobilités Opens T3b Tramway Extension

Île-de-France Mobilités Opens T3b Tramway Extension

On 5 April, Île-de-France Mobilités commenced passenger services on the T3b tramway extension to Porte Dauphine in Paris. 

UK: Network Rail Completes Hope Valley Railway Upgrade

UK: Network Rail Completes Hope Valley Railway Upgrade

Network Rail has completed the 150 million GBP Hope Valley Railway Upgrade project to enhance journeys between Manchester and Sheffield.

Switzerland: Alstom to Service 250 SBB IC2000 Rail Cars

Switzerland: Alstom to Service 250 SBB IC2000 Rail Cars

Alstom has won a service contract to recondition 250 IC2000 rail cars for Swiss Federal Railways (SBB).

LA Metro Completes Tunnelling for D Line Subway Extension

LA Metro Completes Tunnelling for D Line Subway Extension

The Los Angeles County Metropolitan Transportation Authority (LA Metro) has completed tunnelling for the D Line Subway Extension Project.

Amtrak Selects Delivery Partner for Frederick Douglass Tunnel Program

Amtrak Selects Delivery Partner for Frederick Douglass Tunnel Pro...

Amtrak has awarded a 'Delivery Partner' contract to a team comprised of AECOM and Jacobs to support the Frederick Douglass Tunnel Program. 

Alstom Delivers New T1 Tram to Île-de-France

Alstom Delivers New T1 Tram to Île-de-France

Alstom has delivered the first new TW20 tram for the T1 tramway line in Île-de-France to complete testing prior to passenger service.

Hitachi Rail Unveils Long-Distance Hybrid Battery Train

Hitachi Rail Unveils Long-Distance Hybrid Battery Train

Hitachi Rail and Trenitalia have unveiled the long-distance version of Europe’s first hybrid battery-powered train.

Network Rail to Invest £2.8bn in Climate Resilience

Network Rail to Invest £2.8bn in Climate Resilience

Network Rail is investing around 2.8 billion GBP in activities and technology to help cope with extreme weather and climate change. 

$2.4 Billion in CRISI Grants to Improve US Rail Infrastructure

$2.4 Billion in CRISI Grants to Improve US Rail Infrastructure

The FRA has announced over 2.4 billion USD in Consolidated Rail Infrastructure and Safety Improvements (CRISI) Program grants.

UK Government Advances Development of Northern Powerhouse Rail

UK Government Advances Development of Northern Powerhouse Rail

The UK government has presented the next phase of development for the Northern Powerhouse Rail project between Liverpool and Manchester.

Canada: Metrolinx Awards Service Contract to Siemens Mobility

Canada: Metrolinx Awards Service Contract to Siemens Mobility

Siemens Mobility has been awarded a further service contract from Canadian operator, Metrolinx in the Greater Toronto and Hamilton Area. 

HS2 Celebrates Final Breakthrough for Chiltern Tunnel

HS2 Celebrates Final Breakthrough for Chiltern Tunnel

Tunnel boring machine (TBM) Cecilia has completed the final breakthrough for HS2’s longest tunnel under Chiltern Hills. 

Caltrain Retires Diesel Trains Ahead of Electrified Service Launch

Caltrain Retires Diesel Trains Ahead of Electrified Service Launc...

Caltrain has retired 32 diesel passenger cars ahead of the launch of its new electric fleet in autumn 2024.

RFQ for Eglinton Crosstown West Extension Stations, Rail and Systems

RFQ for Eglinton Crosstown West Extension Stations, Rail and Syst...

The Ontario government has issued a RFQ for the design and construction of seven stations along the Eglinton Crosstown West Extension (ECWE). 

UK: Network Rail Reviews 5 Years of CP6

UK: Network Rail Reviews 5 Years of CP6

Network Rail has presented a review of Control Period 6 (CP6), which started on 1 April 2019 and is set to end on 31 March 2024. 

Stadler’s FLIRT H2 Hydrogen Train Sets New Guinness World Record

Stadler’s FLIRT H2 Hydrogen Train Sets New Guinness World R...

Stadler’s hydrogen-powered FLIRT H2 train has earned a new Guinness World Record for travelling 1,741.7 miles without refuelling.

Alstom to Fulfil X-Trafik Maintenance Contract with VR Sverige AB

Alstom to Fulfil X-Trafik Maintenance Contract with VR Sverige AB

Alstom has been awarded a new maintenance contract for a set of nine X-trafik trains in the Gävleborg region of Sweden.

World Passenger Festival Releases Exciting 2024 Agenda

World Passenger Festival Releases Exciting 2024 Agenda

World Passenger Festival has announced that the agenda for the upcoming 2024 event has been officially released.

UK: CrossCountry Unveils Plans to Transform Fleet by May 2025

UK: CrossCountry Unveils Plans to Transform Fleet by May 2025

UK rail operator, CrossCountry has unveiled plans to expand its fleet and transform the customer experience by May 2025.

ÖBB Orders 19 Additional Railjet Trains from Siemens Mobility

ÖBB Orders 19 Additional Railjet Trains from Siemens Mobility

ÖBB has ordered an additional 19 Railjet trains from Siemens Mobility, alongside putting the first new-generation unit into operation. 

FirstGroup Responds to TfN’s Call to End Avanti West Coast Contract

FirstGroup Responds to TfN’s Call to End Avanti West Coast ...

A FirstGroup spokesperson has responded to Transport for the North's motion calling for the termination of Avanti West Coast’s contract.

East Midlands Railway Commences £60 Million Refurbishment Project

East Midlands Railway Commences £60 Million Refurbishment Project

East Midlands Railway (EMR) has announced the start of a 60 million GBP refurbishment project for its Connect and Regional fleet.

InnoTrans 2024 Emphasises Focus on Sustainability

InnoTrans 2024 Emphasises Focus on Sustainability

From 24 to 27 September 2024, InnoTrans will take place with a strong emphasis on sustainability, both at the event and in the industry. 

Transport for the North Votes to Terminate Avanti West Coast Contract

Transport for the North Votes to Terminate Avanti West Coast Cont...

Transport for the North has passed a motion to write to the Secretary of State calling for the termination of Avanti West Coast’s contract.

SNCF Réseau Advances Development of FRMCS-5G

SNCF Réseau Advances Development of FRMCS-5G

SNCF Réseau has provided an update on the development of FRMCS-5G through its involvement in prototype projects across Europe.

Amtrak Begins Harrisburg Line Track Renewal Project in Pennsylvania

Amtrak Begins Harrisburg Line Track Renewal Project in Pennsylvan...

Amtrak has begun a 122 million USD track maintenance project to renew the Harrisburg Line in Pennsylvania. 

UK: GWR Commences Fast-Charging Battery-Powered Train Trial

UK: GWR Commences Fast-Charging Battery-Powered Train Trial

Great Western Railway has officially commenced its fast-charging battery-powered train trial on the Greenford branch line.

Testing Milestone Achieved on Sydney Metro City & Southwest Line

Testing Milestone Achieved on Sydney Metro City & Southwest L...

The 45 trains that will operate on the Sydney Metro City & Southwest line have now completed tests between Tallawong and Sydenham. 

Siemens Delivers Final ICE 4 Train to Deutsche Bahn

Siemens Delivers Final ICE 4 Train to Deutsche Bahn

Deutsche Bahn (DB) has announced that its ICE 4 fleet is now complete with the delivery of the 137th train.

Sydney Build: Championing Diversity, Inclusion & Innovation

Sydney Build: Championing Diversity, Inclusion & Innovation

Sydney Build Expo announces groundbreaking initiatives aimed at driving positive change across the industry, including Women in Construction. 

US: Planning and Development Grants Support Intercity Passenger Rail Services

US: Planning and Development Grants Support Intercity Passenger R...

The US Department of Transportation has awarded 900,000 USD to three agencies to enhance intercity passenger rail services.

Netherlands: Qbuzz Orders New Commuter Trains from CAF

Netherlands: Qbuzz Orders New Commuter Trains from CAF

CAF has been awarded a contract to supply 10 commuter trains to Qbuzz, which is part of the FS Group in the Netherlands. 

UK: Electric Train Tested between Manchester and Stalybridge

UK: Electric Train Tested between Manchester and Stalybridge

An electric train has completed a test run between Manchester and Stalybridge for the first time as part of the Transpennine Route Upgrade.

Caltrain Expands Its Electric Train Testing Area

Caltrain Expands Its Electric Train Testing Area

Caltrain has successfully tested its electric trains and overhead wires between Redwood City and Mountain View for the first time.

UK: New Train Maintenance Depot to Be Built in Shipley

UK: New Train Maintenance Depot to Be Built in Shipley

UK Rail Minister Huw Merriman has confirmed plans to build a new maintenance facility in Shipley, West Yorkshire.

AECOM Publishes New High-Speed Rail Research

AECOM Publishes New High-Speed Rail Research

AECOM has published a new report outlining the best practices for the successful delivery of high-speed rail systems. 

US: 55 Siemens LRVs Ordered for St. Louis

US: 55 Siemens LRVs Ordered for St. Louis

Siemens Mobility has been selected to deliver 55 S200 high-floor light rail vehicles (LRVs) to Metro Transit in St. Louis. 

Alstom to Host Railway Interior Innovation Summit 2024

Alstom to Host Railway Interior Innovation Summit 2024

RedCabin has announced that the Railway Interior Innovation Summit 2024, taking place in Montreal in April, will be hosted by Alstom. 

Alstom Plans Open Access Rail Service in England and Wales

Alstom Plans Open Access Rail Service in England and Wales

Alstom and SLC Rail have partnered to deliver a new open access rail service between North Wales, Shropshire, the Midlands and London. 

Biden-Harris Administration Proposes $4 Billion for Key Transit Projects

Biden-Harris Administration Proposes $4 Billion for Key Transit P...

The Biden-Harris Administration has announced nearly 4 billion USD in federal support for 14 transit construction projects.

France: Alstom to Extend Le Mans Citadis Trams

France: Alstom to Extend Le Mans Citadis Trams

Alstom has been awarded a contract by Le Mans Métropole to extend the length of 34 Citadis trams in Le Mans, France.

China: CRRC Delivers First Train for Rail Transit Ziyang Line

China: CRRC Delivers First Train for Rail Transit Ziyang Line

The first train made by CRRC for the Rail Transit Ziyang Line in China has been delivered.

Sweden: EuroMaint Opens Maintenance Centre in Nässjö

Sweden: EuroMaint Opens Maintenance Centre in Nässjö

CAF's Swedish train maintenance company, EuroMaint, has opened a modern 35.000 square-metre maintenance centre in Nässjö. 

ABB to Supply Traction Package for Queensland’s New Trains

ABB to Supply Traction Package for Queensland’s New Trains

ABB has been awarded a 150 million AUD contract to power trains for Australia’s Queensland Train Manufacturing Program (QTMP). 

Alstom to Supply a Further 103 MF19 Metro Trains in Paris

Alstom to Supply a Further 103 MF19 Metro Trains in Paris

Alstom has received an order to supply an additional 103 MF19 new-generation metro trains for RATP in Paris, France. 

Federal Funding to Deliver New Rail Services in Colarado

Federal Funding to Deliver New Rail Services in Colarado

With federal funding from the Bipartisan Infrastructure Investment and Jobs Act, new passenger rail services are set to launch in Colorado. 

Alstom to Supply 20 Additional Movia C30 Metro Trains for Stockholm

Alstom to Supply 20 Additional Movia C30 Metro Trains for Stockho...

Alstom has been contracted to supply an additional 20 Movia C30 metro trains for SL in Stockholm, Sweden.

Washington Metro to Present New Hitachi 8000 Series Rail Cars

Washington Metro to Present New Hitachi 8000 Series Rail Cars

At a preview event, the Washington Metropolitan Area Transit Authority is displaying its 8000 series rail cars manufactured by Hitachi Rail. 

Open Access Services from London to Stirling Gain ORR Approval

Open Access Services from London to Stirling Gain ORR Approval

ORR has provided approval for Grand Union Trains to launch an open access rail service between London and Stirling, Scotland from June 2025.

Brightline to Open New Rail Station in Stuart, Florida

Brightline to Open New Rail Station in Stuart, Florida

Brightline has announced plans to open a new intercity rail station in the City of Stuart in Martin County, Florida. 

Australia’s Largest Construction and Design Show Returns to ICC Sydney in May

Australia’s Largest Construction and Design Show Returns to ICC S...

Sydney Build is set for its biggest edition yet, with 15 conference stages, 500+ exhibitors and key speakers from across the industry.

UK to Net Zero Requires 30% Increase in Rail Travel, Trainline Reports

UK to Net Zero Requires 30% Increase in Rail Travel, Trainline Re...

Trainline has published a new report declaring that a 30% increase in rail travel is required by 2035 for the UK to meet its net zero goals.

AECOM to Provide Design Services for Toronto’s Ontario Line

AECOM to Provide Design Services for Toronto’s Ontario Line

AECOM has been selected to provide design services for the Ontario Line’s Pape Tunnel and Underground Stations (PTUS) package. 

HS2 Celebrates Breakthrough for Its Longest Tunnel

HS2 Celebrates Breakthrough for Its Longest Tunnel

Tunnel boring machine (TBM) Florence has completed a 10-mile drive under the Chilterns to excavate the longest tunnel for the HS2 project. 

Stadler to Build New Train Commissioning Centre in Hennigsdorf

Stadler to Build New Train Commissioning Centre in Hennigsdorf

Stadler has announced it will be constructing a new commissioning centre for trains in the district of Oberhavel in Brandenburg.

UK: AECOM to Design Mid Cornwall Metro Project

UK: AECOM to Design Mid Cornwall Metro Project

AECOM has been contracted to undertake the detailed design stage for the Mid Cornwall Metro project in the UK. 

Alstom Modernises 270 Metro Cars for Stockholm

Alstom Modernises 270 Metro Cars for Stockholm

Alstom has successfully modernised 270 C20 cars for the Stockholm Metro in Sweden. 

UK: Siemens Mobility Invests in New Chippenham Factory

UK: Siemens Mobility Invests in New Chippenham Factory

Siemens Mobility is investing 115 million EUR in building a new digital engineering factory and R&D centre in Chippenham, UK.

Cargounit Orders Vectron and Smartron Locomotives from Siemens Mobility

Cargounit Orders Vectron and Smartron Locomotives from Siemens Mo...

Locomotive leasing company, Cargounit has signed an agreement with Siemens Mobility for up to 100 Vectron and Smartron locomotives. 

Initial Demolition Begins for Amtrak’s Frederick Douglass Tunnel Program

Initial Demolition Begins for Amtrak’s Frederick Douglass T...

Amtrak has provided an update on the Frederick Douglass Tunnel Program, with initial demolition having begun in Baltimore. 

Italy: Hitachi Rail to Supply 22 Metro Trains in Naples

Italy: Hitachi Rail to Supply 22 Metro Trains in Naples

Hitachi Rail has gained a new contract from the Municipality of Naples to supply 22 new-generation trains for Naples Metro Line 6.

UK: Work to Commence on Delivering Midlands Rail Hub

UK: Work to Commence on Delivering Midlands Rail Hub

The UK Department for Transport (DfT) has provided an initial 123 million GBP in funding for work to begin on the Midlands Rail Hub.

Canada: Metrolinx Awards Tunnelling Contract for Eglinton Crosstown West Extension

Canada: Metrolinx Awards Tunnelling Contract for Eglinton Crossto...

Metrolinx has contracted Strabag to design and build the second underground segment of the Eglinton Crosstown West Extension through Toronto. 

HS2 Launches TBM Emily to Bore Northolt Tunnel

HS2 Launches TBM Emily to Bore Northolt Tunnel

HS2 has launched its third giant tunnel boring machine (TBM) in London that will construct the Northolt Tunnel.

New Zealand: Stadler to Supply 33 Locomotives to KiwiRail

New Zealand: Stadler to Supply 33 Locomotives to KiwiRail

KiwiRail and Stadler have signed an additional two contracts for the supply of 33 locomotives in New Zealand. 

Alstom Commences Trainset Production for Delhi Metro Phase IV

Alstom Commences Trainset Production for Delhi Metro Phase IV

Alstom has commenced production for an order of 52 six-car trainsets for the Delhi Metro Rail Corporation Phase IV.

UK Government Reallocates £4.7 Billion of HS2 Funding

UK Government Reallocates £4.7 Billion of HS2 Funding

Local authorities in the North and the Midlands will receive 4.7 billion GBP in reallocated HS2 funding to improve transport connections. 

Elevated Guideway and Stations Contract Awarded for Toronto’s Ontario Line

Elevated Guideway and Stations Contract Awarded for Toronto’...

Infrastructure Ontario and Metrolinx have contracted Trillium Guideway Partners (TGP) to deliver the Ontario Line Elevated Guideway and Stations contract.

£21.4 Million Investment for Manchester’s Metrolink Tram Network

£21.4 Million Investment for Manchester’s Metrolink Tram Ne...

Metrolink is investing a further 21.4 million GBP to enhance Greater Manchester's light rail network over the next 12 months. 

US: $631 Million in Federal Funding to Buy New Railcars

US: $631 Million in Federal Funding to Buy New Railcars

The US DOT's Federal Transit Administration (FTA) has announced 631 million USD in grants for transit agencies to buy new railcars. 

Rail Baltica Awards Mainline Construction Contracts in Estonia

Rail Baltica Awards Mainline Construction Contracts in Estonia

Rail Baltic Estonia has awarded construction contracts to Verston OÜ and Järelpinge Inseneribüroo OÜ for the mainline in Kohila and Rapla.

Metra Orders 16 Battery-Electric Stadler Trains for Chicago

Metra Orders 16 Battery-Electric Stadler Trains for Chicago

Metra has awarded a contract to Stadler to supply 16 battery-electric trains for operation in Chicago and the surrounding region.

Siemens Mobility to Supply up to 250 Locomotives to Railpool

Siemens Mobility to Supply up to 250 Locomotives to Railpool

Siemens Mobility has signed a framework agreement with leasing company, Railpool for the delivery of up to 250 Vectron locomotives.

India: Alstom Delivers First Trainset for Meerut Metro Project

India: Alstom Delivers First Trainset for Meerut Metro Project

Alstom has delivered the first trainset to the National Capital Region Transport Corporation (NCRTC) for the Meerut Metro project in India. 

Invitation Letter for Rail + Metro China 2024

Invitation Letter for Rail + Metro China 2024

This year's Rail + Metro China will feature in-depth discussions on key topics such as trends and developments in urban rail transit.

London Overground Lines Assigned New Names and Colours

London Overground Lines Assigned New Names and Colours

Transport for London (TfL) has announced that London’s Overground lines will be given new names and colours for the first time. 

UK DfT Publishes Draft Rail Reform Bill

UK DfT Publishes Draft Rail Reform Bill

The UK's Department for Transportation (DfT) has published the Draft Rail Reform Bill as part of its vision for the future of rail.

Wales: New Railway Station Planned for Vale of Glamorgan

Wales: New Railway Station Planned for Vale of Glamorgan

The UK government has announced its support for establishing a new railway station at St Athan in the Vale of Glamorgan, Wales. 

Contact Wales: New Railway Station Planned for Vale of Glamorgan

Use the form opposite to get in touch with Wales: New Railway Station Planned for Vale of Glamorgan directly to discuss any requirements you might have.








    We'd love to send you the latest news and information from the world of Railway-News. Please tick the box if you agree to receive them.

    For your peace of mind here is a link to our Privacy Policy.

    By submitting this form, you consent to allow Railway-News to store and process this information.

    Subscribe
    Follow Railway-News on LinkedIn
    Follow Railway-News on Twitter