The winners of the major construction contracts for Britain’s new railway were announced today, 17 July 2017, with the £6.6 billion contracts supporting 16,000 jobs across the country.

The huge infrastructure investment covers the main civil engineering work on the first phase of HS2 between London and Birmingham – including construction of tunnels, bridges, embankments and viaducts.

Construction Contracts for HS2 Phase One
Curzon Street Station © hs2.org.uk

Transport Secretary Chris Grayling announced the decision to award contracts today, which will mean the new high speed link reaching Birmingham by 2026. Grayling commented:

This is a hugely important step in the construction of Britain’s new railway and underlines this government’s determination to deliver an economy that works for all.

HS2 will deliver vital links between some of our country’s biggest cities, helping to drive economic growth and productivity in the north and midlands.

As well as providing desperately needed new seats and better connecting our major cities, HS2 will help rebalance our economy.

We will now get on with building the railway, while continuing to ensure affected communities get appropriate support and are treated with fairness, compassion and respect.

Construction Contracts for HS2 Phase One

In February, Parliament granted powers to construct the Phase One route from London Euston to Birmingham, with the route opening in 2026. The winning bidders to build the first phase of the route are:

Area South:

  • Euston Tunnels and Approaches – SCS JV (Skanska Construction UK Ltd, Costain Ltd, STRABAG AG)
  • Northolt Tunnels – SCS JV (Skanska Construction UK Ltd, Costain Ltd, STRABAG AG)

Area Central:

  • Chiltern Tunnels and Colne Valley Viaduct – Align JV (Bouygues Travaux Publics, VolkerFitzpatrick, Sir Robert McAlpine)
  • North Portal Chiltern Tunnels to Brackley – CEK JV (Carillion Construction Ltd, Eiffage Genie Civil SA, Kier Infrastructure and Overseas Ltd)
  • Brackley to South Portal of Long Itchington Wood Green Tunnel – CEK JV (Carillion Construction Ltd, Eiffage Genie Civil SA, Kier Infrastructure and Overseas Ltd)

Area North:

  • Long Itchington Wood Green Tunnel to Delta Junction and Birmingham Spur – BBV JV (Balfour Beatty Group Ltd, VINCI Construction Grands Projets, VINCI Construction UK Ltd, VINCI Construction Terrassement)
  • Delta Junction to WCML Tie-In – BBV JV (Balfour Beatty Group Ltd, VINCI Construction Grands Projets, VINCI Construction UK Ltd, VINCI Construction Terrassement)
  • Preparatory works are already underway, with main construction work starting in 2018/19 following a period of detailed design work.

More Seats and Extra Local Services

HS2 could carry more than 300,000 people a day. And with fast trains using the new line, there will be extra space for more trains on the existing rail network.

Benefits will be felt across the network with trains running as far as Scotland and the number of seats available out of Euston in peak hours more than doubled.

In total, construction of the full HS2 route to the north-west and Yorkshire will create up to 25,000 jobs and 2,000 apprenticeships. Another 3,000 people will operate HS2 and it is estimated that growth around new HS2 stations will create another 100,000 jobs.

Original article © Department for Transport.

FOR ALL THE LATEST INFORMATION, NEWS, IMAGES, VIDEOS AND ARTICLES ON ALL ASPECTS OF INFRASTRUCTURE, PLEASE CLICK HERE

 

Tags

More News

Get in touch

Please fill in the contact form opposite. A member of the team will be in touch shortly.








    Advertise with UsGeneral EnquiryEditorial Request

    We'd love to send you the latest news and information from the world of Railway-News. Please tick the box if you agree to receive them.

    For your peace of mind here is a link to our Privacy Policy.

    By submitting this form, you consent to allow Railway-News to store and process this information.