New Train Manufacturing Plant in South Africa Nears Completion

Alstom and its partners of its local South African joint venture company Gibela, have now moved since last week in the new train manufacturing plant in Dunnottar, Ekurhuleni which has now become Gibela’s corporate offices too.

The plant construction is now almost finalised, on schedule less than two years after the start of the construction.

New Train Manufacturing Plant in South Africa
Gibela will manufacture 580 six-car X-Trapolis Mega commuter trains to be built over the next 10 years for the Passenger Rail Agency of South Africa (PRASA) © Gibela

Train Manufacturing Plant, Dunnottar

Gibela’s current 400+ fulltime employees are now based at the complex at 2 Shosholoza Avenue, and work begins on the manufacture of the first of 580 six-car X-Trapolis Mega commuter trains to be built over the next 10 years for the Passenger Rail Agency of South Africa (PRASA). At peak production more than 1,000 employees are expected to be manufacturing an average of five trains a month. Moreover, of 65 apprentices selected during 2017, most have already begun their training at the Gibela training centre.

By the end of the first quarter of 2018, the first train’s car body shell – essentially, its metal panel-clad metal frame – is expected to be completed. By the end of 2018, the first South African-built train should be ready for delivery to PRASA.

Didier Pfleger, Senior Vice-President for Middle-East and Africa, said:

Alstom is very proud of the progress made by Gibela in less than 2 years to finalize the construction of the plant, in Dunnottar. The completion is underway for March 2018. All teams are now on board and ready to start the manufacturing in a brand new factory with new staff and a new supplier base.

First South African-Built Trains

18 of 20 trains built at Alstom’s Lapa, Brazil factory – using South African materials and involving South Africans – have been in commercial service part of 2017 and are estimated to have already clocked up, in total, more than half a million kilometres.

One of the two trains built in Brazil – the other one will still be used for testing purposes – will now be based at Gibela’s  training centre in Dunnottar, where it will be instrumental in the training of some 19,500 artisans and technicians. To meet its local content commitment of at least 65% of contract value, Gibela has on-boarded so far 54 South African suppliers to supply materials, parts and services. More than 4,700 South African jobs are being supported by the company’s activities.

Alstom has been present in South Africa for many years and was awarded this €4 billion contract by PRASA in October 2013. The contract also includes 19-year service agreement.

Original article © Alstom.

FOR ALL THE LATEST INFORMATION, NEWS, IMAGES, VIDEOS AND ARTICLES ON ALL ASPECTS OF BUILDINGS AND STRUCTURES, PLEASE CLICK HERE

Get your news featured on Railway-News

Please fill in the contact form opposite. A member of the team will be in touch shortly.







    We'd love to send you the latest news and information from the world of Railway-News. Please tick the box if you agree to receive them.

    For your peace of mind here is a link to our Privacy Policy.

    By submitting this form, you consent to allow Railway-News to store and process this information.

    Subscribe
    Follow Railway-News on LinkedIn
    Follow Railway-News on Twitter