HS2 Ltd has begun preparations to move to the next major phase of civil engineering works on the Curzon approaches – the final mile stretch of of HS2’s entry Birmingham city centre.
Works are now underway to install a set of five interconnected viaducts, which, together, form the approaches themselves.

Later this week, engineers will then begin laying concrete slabs to create solid decks on each of the structures ahead of railway tracks being laid. These slabs have been manufactured at Balfour Beatty VINCI’s (BBV’s) purpose-built factory in Kingsbury, Warwickshire, and the production line has now switched to creating precision-design slabs for the approaches following four years manufacturing segments for the Delta Junction viaducts.
Installation will be driven by a 125-tonne gantry crane, which has already been lifted into position above the Lawley Middleway viaduct. Now, the crane will begin its 18-month task, laying the slabs one at a time as it works its way from Lawley Middleway viaduct, to Curzon 2, Curzon 1 and finally Duddeston Junction viaduct.
Greg Sugden, HS2 Ltd’s Head of Delivery for the Curzon Approaches said:This is a huge moment for the Curzon approaches team, as we begin what is essentially the last major phase of civil engineering works on this section of the route.
It’s a test of skill and precision, as we must ensure that when the gantry crane arrives at each structure, we’re ready for the deck installation works to begin.
It will take around 18 months to lay the decks, then HS2’s new elevated gateway into Birmingham will be structurally complete.
In order to preserve the safety of the public, as well as those at work on the project, a series of temporary nighttime road closures will be put in place while the deck slabs are laid above the road and public walkways.
This will affect the Lawley Middleway (A4540) between Garrison Circus and Curzon Circus, and a northbound only closure will be in place from 22:00 until 06:00 each night from Saturday 21 November until Sunday 6 December. Elsewhere, a full closure in both directions will be in effect from 22:00 until 06:00 each night from Wednesday 25 November until Wednesday 2 December and a southbound only closure from 22:00 until 06:00 each night from Thursday 3 December until Sunday 6 December.
Malik Kayatas, Section Manager at Balfour Beatty VINCI said:A 125-tonne gantry crane will begin installing deck slabs along a series of interconnected viaducts in Birmingham this week.
Sitting on top of the structures, it will move outwards from the city centre on an 18-month journey, marking the next exciting phase of this project.